Hi Tech Health

Hi Tech Health Maroochydore

The brief was for the renovations.

This is a call center for one of the fastest growing companies in Australia, and the renovations had to done while they were on the phones and the Hub Server was not to be interrupted. The power was not to be shut off at any time.

Again Military precision was called for.

5 o’clock Friday afternoon the demolition started, with temporary power to the server.

By Monday  morning the office was back in shape but we still had the glass partitions, office cubicles, and carpet to go down and the ceiling tiles to be replaced. This was all done during working hours the next week, with a busy call center at arms length.

Most of the noise work was done between 5 and 9 o’clock in the morning, before the phone started to ring. So if you have a difficult job or situation  call us.